Sweden’s transport administration has resumed planning for the Härryda section of the Gothenburg–Borås railway. Work now turns to detailed route options for roughly half the corridor and to consultation on a branch serving Mölnlycke.
Trafikverket confirmed on November 16 that it had resumed planning for about 30 kilometers of the proposed Gothenburg–Borås railway through Härryda municipality. Sweden’s government gave its approval in principle for the roughly 60-kilometer railway in June. The milestone in November was the return to detailed rail planning in Härryda, where the agency still has to establish where the tracks would go and how they would fit into the landscape.
A Straighter Route Through Uneven Ground
The new line is intended to follow a much straighter alignment than the existing Kust till kust railway. In a hilly area where the corridor crosses settlements and countryside, a straighter route can require bridges or tunnels to hold the line and grade. Each alignment changes which properties, landscapes and heritage sites are affected. Comparing alignments also means tracing where construction would need temporary access and where work would continue near existing homes or roads.
Trafikverket scheduled local meetings in Landvetter, Mölnlycke and Rävlanda around the end of November and the start of December. People living along a potential alignment can identify local paths, access points and other features planners need to account for before drawing a detailed route.
Mölnlycke Has Its Own Planning Step
A separate branch would connect Mölnlycke to the new railway. Trafikverket says it needs a decision from the County Administrative Board to move to the next planning step for that branch. The agency plans an initial consultation around the turn of the year. It expects to present route options, including for the branch, in autumn 2027. Its autumn 2028 timetable calls for a detailed proposal that can identify affected properties and the land needed during construction.
That sequence gives residents and local authorities two different points to assess the project. The first is a choice among workable alignments. The second is a plan detailed enough to see what each crossing, work site or land requirement means on the ground.
Take-Out
The June decision cleared the way for planning to resume. The next meaningful evidence will be route alternatives that show how the railway and the Mölnlycke branch affect land, crossings and local access.
Questions and answers
What readers should know
- What did Trafikverket resume?
- Planning for the approximately 30-kilometer stretch of the Gothenburg–Borås railway through Härryda.
- How long is the whole proposed railway?
- About 60 kilometers.
- What would the branch do?
- It would connect Mölnlycke to the proposed new railway.
- What decision does the branch still need?
- Trafikverket says it needs a decision from the County Administrative Board before taking the next planning step.
- When does the agency expect to show more detail?
- It expects initial options in autumn 2027 and a detailed route proposal in autumn 2028.