Argentina has set interim operating rules for hydroelectric complexes moving toward new concessions. Existing operators can accept temporary terms, while a separate minimum operating period gives the state time to protect service if an incumbent declines.
Argentina’s Decree 1349/2026 took effect on November 11, the day it appeared in the official gazette. It addresses the gap between existing hydropower concessions and the point when a new operator can take over. A tender can establish who wins the next contract, but the generating complexes still need someone responsible for operating them while the process runs.
What the Incumbents Can Agree To
The decree covers 11 plants grouped under five incumbent concessionaires. They include Futaleufú in Chubut, the Diamante system in Mendoza and facilities in Salta, Santiago del Estero and Tucumán. An operator listed in the decree’s annex has seven calendar days from entry into force to send the Energy Secretariat a letter accepting the interim terms. If it sends the letter, it can continue operating under the applicable concession and decree until April 30, 2027, or until possession passes through the tender process, whichever happens first.
The possession trigger makes a difference. A winning bidder can be selected before it takes responsibility for operating the facility. Linking the interim arrangement to possession gives the incumbent a defined role across that interval when handover happens before the April deadline. The date cap also gives the state a reason to keep the procurement and transfer timetable visible. Readers following the transition should distinguish between opening a competition, selecting an operator and transferring possession.
If an Operator Declines
An incumbent that does not send the acceptance letter remains obliged to generate electricity for at least 45 working days. The national government is to use that period to take the steps needed to keep service going. That fallback applies a different clock from the seven calendar days allowed for acceptance. It gives the government a window to act without assuming that all incumbents will agree to the temporary terms.
The decree delegates authority to the Energy Secretariat to set the terms of national and international tenders and to award and sign new concessions. Those powers bring tender design and contracting under the same office. The decree establishes the interim obligations and the route to new contracts. Tender announcements and notices of possession will show how quickly individual facilities move through it.
Take-Out
Argentina links the end of the temporary concession period to actual possession, with a date cap. The fallback for a declined extension gives the state a separate window to make continuity arrangements.
Questions and answers
What readers should know
- When did the decree take effect?
- It took effect when published in the official gazette on November 11, 2026.
- How long do existing operators have to accept?
- Seven calendar days from the decree’s entry into force.
- When can accepted interim terms end?
- On April 30, 2027 at the latest, or earlier when possession passes under the tender.
- What happens if an incumbent declines?
- It must continue generating for at least 45 working days while the government takes steps to preserve service continuity.
- Who sets the tender terms?
- The Energy Secretariat within the Ministry of Economy.