The Hollandse Delta water board scheduled November work on underwater dike slopes at two sites. Crews will place rock from vessels, addressing a threat to the stability of the defenses that can develop below an intact dike crest.
Waterschap Hollandse Delta set November 9 as the start date for reinforcing submerged slopes at the Hongerlandsedijk on the Oude Maas and near the Brielse Maasdijk on the Hartel Canal. Work across the Oude Maas near Hoogvliet’s Vossedijk park is scheduled for early January 2027. The water board’s October 30 notice expects this group of works to finish in March 2027.
Sand movement below the waterline
A dike can appear sound from its crest even when the underwater part of its slope has become vulnerable. The water board identified locations where underwater sand can move away from the bank in a process known in Dutch as zettingsvloeiing. As that material moves, it can change the shape of the submerged slope and reduce the stability of the dike above it. Inspection from land alone gives a limited view of that risk.
The project will place large stone over the underwater slope at the locations that need protection. Rock helps hold the underlying material in place. The work consequently addresses the part of the defense that supports the visible bank. The scheme covers five locations across the board’s area, with work already undertaken at Ouddorp and Middelharnis as part of the same program.
Placing rock from the water
The contractor will bring rock and other materials by vessel and set the stone down with a crane on a pontoon. The water board says project trucks will therefore stay off the Hongerlandsedijk and surrounding residential streets. Access from the water also lets crews reach the submerged work face directly. The challenge is to place enough rock in the right locations when much of the finished shape cannot be seen from above the surface.
The schedule identifies where and when crews plan to work. What ultimately matters for the defense is whether the rock forms the intended profile across the vulnerable stretch, including where the new protection meets the existing bank.
Take-Out
Reinforcing a dike can mean working below the waterline. Hollandse Delta is treating the submerged slopes where sand can move and weaken the shape that supports the visible defense.
Questions and answers
What readers should know
- What work was scheduled to start on November 9?
- Reinforcement at the Hongerlandsedijk in Spijkenisse and near the Brielse Maasdijk on the Hartel Canal.
- What can weaken the dike below water?
- Sand can move away from parts of the submerged slope, changing the shape that supports the bank.
- How will the contractor place the rock?
- Work vessels and pontoons will carry the rock, and a crane will place it along the submerged slope.
- Where will the next work take place?
- The board scheduled work across the Oude Maas at Vossedijk park in Hoogvliet for early January 2027.
- Does this work require trucks on the Hongerlandsedijk?
- The board says materials will arrive by water, so project trucks will stay off that dike and the neighboring residential streets.