Brazil’s Transmission Auction Sets the Price of Future Service

Read the analysis
Steel electricity pylons and power lines recede across a flat landscape.
High-voltage transmission towers under a cloudy sky. MonikaP · https://pixabay.com/service/license-summary/

Brazil’s electricity regulator awarded all eight lots in its October transmission auction. Winning bids cut proposed annual revenue by about half against the regulator’s ceiling, while the resulting concessions still require operators to build, maintain and put assets into service.

Brazil’s October 30 transmission auction settled how much the winners bid to earn for providing a defined network service. Across the eight lots, the winning annual revenue bids came to about R$811.1 million, compared with the regulator’s ceiling of about R$1.625 billion. That 50.10 percent discount measures the difference between two annual revenue figures. It is the starting point for reading the award and the obligations that go with it.

What the Bid Buys

Brazil’s electricity regulator, ANEEL, sets a maximum annual permitted revenue for each lot. Bidders offer to provide the service for less than that ceiling. The offer commits the winning operator to a revenue level for a package that can include building equipment, bringing it into commercial operation and maintaining it. The value under competition is the annual payment associated with that obligation.

The cost of building the facilities belongs in a separate column. A bidder may be able to lower its revenue offer because it expects to finance, procure or operate the assets on favorable terms. The bid itself does not disclose which part of its business plan made that possible. The regulator’s estimate of consumer savings over the concession periods uses the difference against its revenue ceilings. Household bills also reflect other costs and tariff decisions, so the auction percentage cannot be read as a change in an individual bill.

Why an Auction Lot Can Contain Several Kinds of Work

The October portfolio covered facilities in seven states. It included 1,866 kilometers of new lines, continued operation and maintenance of 483 kilometers of existing lines and substations with 12,694 megavolt-amperes of transformation capacity. A line carries power across the network. A transformer lets power move between voltage levels. Continuity of existing operations can matter just as much as bringing a new circuit into service.

Brazil’s energy planning company, EPE, describes the lots as the product of expansion studies involving the ministry, regulator and national system operator. Those studies identify the network work that needs doing before bids are sought. Putting several assets into one concession gives a bidder an obligation that can be priced together, while the underlying items still need their own engineering, equipment and delivery dates.

A Lot Where the Equipment Explains the Obligation

The eighth lot illustrates how much can sit behind one revenue figure. It calls for three synchronous compensators at the Porto Velho collector substation in Rondônia. These rotating machines help steady voltage on the grid. The operator’s task is to install equipment that can provide that support to the system serving Acre and Rondônia.

ANEEL recorded the winning annual bid for the lot at about R$66.7 million against an initial allowance of about R$128.2 million. It estimated R$753.2 million of investment for the lot and set a 42-month delivery horizon. Comparing those figures directly would mix a yearly payment, a capital estimate and an implementation period. Each figure has a place in assessing the concession, and the service can be judged only once the machines enter operation.

The Clock Starts With the Contracts

The auction result gives operating deadlines ranging from 42 to 60 months for the works, with the concessions running for 30 years from contract signing. Signing gives the parties a date against which to track performance. From there, the evidence that matters includes which assets have moved into construction, which equipment has been installed and which facilities the system can actually use.

An award record and an operating record therefore belong alongside each other. The first shows what the competition secured on price. The second shows whether new lines, substations and voltage support have become available where the expansion studies identified a need.

Take-Out

A transmission auction prices a service obligation. The revenue bid, construction estimate and date when equipment enters operation each answer a different question about what the award delivers.

Questions and answers

What readers should know

How many lots were awarded?
All eight lots offered on October 30 were awarded.
What is annual permitted revenue?
It is the annual remuneration for providing the transmission service defined in a concession.
What does the 50.10 percent discount measure?
It compares the combined winning annual revenue bids with the regulator’s combined revenue ceiling.
What will be installed at Porto Velho?
The eighth lot calls for three synchronous compensators to support reliable transmission operation.
When are new works expected to enter operation?
The auction set a range of 42 to 60 months for commercial operation, measured from contract signing.