Terna Opens Land Review for the Suvereto Grid Redesign

Read the analysis
Electricity pylons crossing a rural landscape
Overhead power lines illustrate the type of infrastructure Terna plans to remove. minka2507 / Pixabay · https://pixabay.com/service/license-summary/

Terna has published a land notice for a proposed grid redesign across three municipalities in Tuscany. Four underground circuits leaving the Suvereto substation would enable the removal of about 32 kilometers of overhead lines and 107 supports.

Terna’s November 12 land notice identifies properties that could be affected by a redesign of the 132-kilovolt network around the Suvereto substation in Tuscany. The Suvereto grid plan is now in the authorization process. The works span Suvereto, Campiglia Marittima, and Piombino. Landowners can now see where the proposal may affect their properties and have 30 days from publication of the notice to send observations to the ministry.

Fewer Kilometers of New Line Than Old

The grid operator proposes putting four circuits from the substation underground, with about 12 kilometers of new cable routes in total. That would allow about 32 kilometers of existing overhead lines and 107 supports to be removed. The two lengths do not describe the same route built in two materials. The plan changes how the lines near the substation are laid out, so the new connections can replace a longer set of existing routes.

Removing overhead lines can free land beneath them; Terna estimates around 96 hectares would be released. Underground routes still need construction access and land rights, and the people affected by the new routes may differ from those who gain from the old lines’ removal. The land notice makes that distribution visible while there is still time to comment on the proposal.

Local Work Tied to a Wider Power Link

The redesign is associated with the new Sa.Co.I.3 electricity link between Italy and Corsica. It addresses the onshore circuits around Suvereto. Delivering the local works will require a route the authorities can approve and a way to transfer the circuits’ service before the redundant lines come down. The November notice does not record approval or a construction start. It does give affected municipalities and landowners the opportunity to test the layout against conditions on the ground before the operator can build it.

Take-Out

The land notice shows where a shorter set of underground circuits could replace a longer overhead network. Affected properties, route approvals, and continuity of supply must be settled before the old lines can come down.

Questions and answers

What readers should know

What has Terna published?
A notice listing parcels that may be affected by the proposed grid works.
What would the project put underground?
Four 132-kilovolt circuits leaving the Suvereto substation, totaling about 12 kilometers.
How much overhead infrastructure could be removed?
About 32 kilometers of overhead lines and 107 supports, according to Terna.
Where are the affected municipalities?
Suvereto, Campiglia Marittima, and Piombino are in Italy’s Livorno province.
Has construction been authorized?
The notice records the start of an authorization process and a chance to submit observations.